How are screw piles installed?

Screw piles are installed by winding a galvanised steel pile into the ground with a torque-motor drive head on an excavator, following the engineer's pile schedule. Each pile is set out from the drawings, wound in until the torque reading proves it has reached its design load, extended if bearing is deeper than the lead section, then cut to level and fitted with a cap or bracket. There is no digging, no spoil and no concrete to cure: a crew installs 20 to 30 piles in a day and the frame or slab can go on straight away. The installation record of every pile's depth and torque goes to the building surveyor.

Prices on this page are indicative ranges for Victoria at the time of writing, not a quote. Based in Keilor East, Melbourne. Working across metropolitan and regional Victoria, New South Wales and South Australia.

Step 1: set-out from the engineer's pile schedule

Every screw pile job starts with the engineer's drawings. The pile schedule lists each pile's position, diameter, the design load it has to carry and the torque that proves it. We set the piles out on the ground from the drawings and the site boundaries, usually with the builder or surveyor's string lines in place, so each pile lands where the bearer, post or slab edge will sit. Before any pile goes in, underground services are located through Before You Dig Australia and marked on the ground.

Step 2: the machine

The pile is driven by a hydraulic torque-motor drive head mounted on an excavator in place of the bucket. We run drive heads on excavators from 1.8 tonne up to 20 tonne (1.8, 3, 5, 8, 10, 15 and 20 t), so the machine is matched to the job: a 1.8 t fits through a gap under 750 mm wide, down the side of a house or onto a sloping block where a bored pier rig or a concrete truck could not go, and the larger machines handle big commercial sites and heavier piles. The drive head turns the pile and reads the torque at the same time, and the operator keeps the pile plumb with the excavator's boom. Because there is no auger, no spoil and no concrete pump, the site footprint is small and the ground around the pile is left undisturbed.

Step 3: winding the pile in

The lead section, the piece with the helical plate on the end, is positioned on the set-out mark and wound into the ground. The helix pulls the pile down the way a screw pulls into timber, so it displaces soil rather than removing it. The operator watches two things: the depth and the torque.

If the pile reaches the end of the lead section before it reaches the required torque, an extension is bolted or welded on and winding continues. Extensions are routine on filled sites and deep reactive clay, which is why screw piles are priced per pile with a depth allowance and any extra extension shown separately.

The torque reading is the proof of capacity. The engineer's chart relates the installation torque to the pile's load capacity for that diameter and soil, so when the gauge reaches the specified figure the pile is at its design load and winding stops. That is the key difference from a bored pier, where you are relying on the depth and the founding material you can see in the hole.

Refusal that comes early, say in the first half metre, usually means rock, an old footing or buried concrete. The pile is backed out and relocated slightly, or the engineer is asked to accept a shorter pile at higher torque, or the obstruction is removed. Refusal that comes late, well past the expected depth, usually means soft fill or wet clay: the pile is extended until the torque is reached, and if that is a long way down the engineer may change the pile diameter or add a pile.

Step 4: cutting to level and fitting caps or brackets

Once every pile is at torque, each shaft is cut to the level on the drawings with a reference laser or a string line. The cap plate or bracket is then welded or bolted on: a flat plate for a slab or pad, a saddle or stirrup bracket for a timber or steel bearer, or an adjustable head where the builder wants to fine-tune the bearer height. Cuts and welds on the galvanised shaft are cold-gal treated.

Step 5: the installation record

We record each pile's number, diameter, final depth, number of extensions and final torque reading. That record goes to the engineer and the building surveyor as evidence that every pile reached its design capacity, and it is what the surveyor signs off against before the frame or slab inspection. Keep a copy with the house documents; it is useful if you extend later.

How long it takes

A crew installs 20 to 30 piles in a normal day on a site with reasonable access. A deck or pergola is usually half a day; a house extension or a sloping-site home is one day; a larger village or park job is scheduled over several days. Because there is no concrete to cure, the frame, bearers or slab can follow immediately, often the same afternoon.

What you need ready before we arrive

  • Access for the excavator: our smallest machine fits through a gap under 750 mm wide, so most side passages work as they are; a fence panel or gate comes out only if it saves time. We confirm this on the site visit.
  • The soil report (geotechnical report). The engineer uses it to size the piles and set the torque, and we check it against what the piles tell us on the day.
  • The engineer's drawings and pile schedule, with the finished pile levels marked.
  • Services located through Before You Dig Australia, with any private services (pool pipes, irrigation, old drains) pointed out to us.
  • Set-out: the builder's string lines or survey pegs, or we set out from the drawings.

What screw piles cost

Price depends on pile diameter, depth to bearing, pile count and access. Rather than repeat the numbers here, see our guide on how much screw piles cost in Victoria, which gives indicative ranges by job type. Every quote we give is fixed and in writing after a site visit and the engineer's drawings.

Questions we get asked

Can screw piles be installed in wet weather?

Yes. Rain does not stop a screw pile job the way it stops a bored pier or a slab pour, because there is no open hole to fill with water and no concrete to protect. The limit is the machine: if the site is too boggy to track an excavator safely we come back when it has dried, but a wet clay site that would delay a pier crew for a week is usually fine for piles.

How close to a fence or an existing house can a screw pile go?

Close. With a compact drive head a pile can typically be installed within about 300 to 500 mm of a fence or an existing wall, which is why screw piles are common for extensions, decks and boundary structures. Where the engineer wants a pile tight against an existing footing, a smaller diameter pile or an offset bracket is specified. We check clearances on the site visit.

Do screw piles need concrete?

No. The pile is the footing. The torque reading proves the load capacity, and the cap or bracket takes the structure directly. Some designs do pour a concrete pad, slab edge or pile cap over the top of the piles, but that is part of the structure above, not something the pile needs to carry load.