How long before you can drive on a new concrete driveway?
Keep cars off a new concrete driveway for seven days and anything heavier, such as a caravan, boat trailer, truck or skip bin, for 28 days. Foot traffic is fine after 24 hours. Concrete keeps gaining strength for weeks after it is poured; at seven days it has reached roughly two-thirds of its design strength, which is enough for a car, and it reaches full strength at 28 days. Driving on it early is the most common cause of cracked and chipped driveways.
Prices on this page are indicative ranges for Victoria at the time of writing, not a quote. Based in Keilor East, Melbourne. Working across metropolitan and regional Victoria, New South Wales and South Australia.
The timeline
- First 24 hours: nothing on it at all. Keep pets, kids and bikes off; the surface marks easily.
- Day 1 to 2: walk on it, carefully. Avoid dragging anything.
- Day 7: cars and light vans, driven straight on and off. No turning the wheels while stationary.
- Day 28: full design strength. Caravans, boats, trucks, skip bins and machinery are fine, provided the slab was designed for them.
Why the wait
Concrete does not dry; it cures, which is a chemical reaction between cement and water that goes on for weeks. Strength rises quickly in the first few days and then more slowly. A car on a three-day-old driveway puts a point load on concrete at around half strength, and the result is a crack along the wheel path or a chipped edge at the crossover that shows up months later.
Weather and curing
Cold, wet Melbourne weather slows the reaction, so in winter be conservative: add a couple of days before cars. Hot, windy days dry the surface too fast, which is why we keep new concrete damp or covered for the first few days. Sealing exposed aggregate usually happens at around day 7 to 14 once the surface has dried out, and the driveway needs a further 24 hours off after sealing.
Other things to avoid in the first month
- Parking in the same spot every day with a heavy vehicle.
- Turning the steering wheel while stopped, which scuffs the surface.
- Dropping tools, trailer jockey wheels or bin wheels on the edges.
- Salt, fertiliser or oil spills before the sealer is on.
Questions we get asked
Can I drive on it after 3 days if I'm careful?
We don't recommend it. At three days the concrete is around half strength, and the damage from an early load usually appears later as a crack you cannot fix.
When can a skip bin or a delivery truck use the driveway?
After 28 days, and only if the driveway was poured at 150 mm with reinforcement to take it. A standard 125 mm residential driveway is not designed for trucks at any age.
Does sealing change the timing?
No for strength, yes for access: after the sealer goes on, keep everything off for 24 hours while it cures.