Do you need a permit for a driveway crossover in Melbourne?

Yes. The crossover is the section of driveway between the kerb and your property boundary, and it sits on council land, so every Melbourne council requires a vehicle crossing permit before it is built, replaced or widened. The permit sets the width, position, profile and concrete specification, and the council inspects the work. Fees are typically $150 to $450 and approval takes one to four weeks depending on the council.

Prices on this page are indicative ranges for Victoria at the time of writing, not a quote. Based in Keilor East, Melbourne. Working across metropolitan and regional Victoria, New South Wales and South Australia.

What the permit covers

The crossover is council infrastructure even though you pay for it. The permit, sometimes called a vehicle crossing permit or asset protection permit, usually fixes:

  • Width: most councils allow 3 to 3.5 m for a single crossover and up to 6 m for a double, with a minimum distance from the neighbour's crossover, street trees, pits and poles.
  • Profile: the council's standard drawing sets the kerb cut, the layback, the thickness (commonly 125 mm residential, 150 mm or more for industrial) and the reinforcement.
  • Position: it must line up with the driveway inside the boundary and keep clear of services.
  • Reinstatement: footpath and nature strip put back to the council's standard.

How it works, step by step

  • Check the council's standard crossover drawing and whether a tree, pit or pole is in the way. Some councils will not allow a crossover within a set distance of a street tree, and relocating a pit is expensive.
  • Apply online with a site sketch showing the proposed crossover, the boundary and any obstacles. We supply the sketch when we are doing the job.
  • Pay the permit fee. Some councils also hold an asset protection bond that is refunded after inspection.
  • Build to the standard drawing. The council inspector may want to see the formwork and steel before the pour, then the finished crossover.
  • Final inspection and sign-off, which releases any bond.

Who lodges it

Either. Most of our customers prefer we lodge it, because the council asks for the sketch, the profile and the contractor's details, and we are the ones who have to build to it. Some councils only accept applications from the property owner, in which case we prepare the paperwork and you submit it. Either way, the fee is passed through at cost and shown on the quote.

Costs beyond the permit

The crossover itself is usually priced with the driveway: typically $1,500 to $4,000 for a residential crossover depending on width, whether an old one has to be removed, and whether the footpath has to be rebuilt across it. Removing a redundant crossover and reinstating the kerb is a separate council requirement when you move the driveway, and councils charge for that too.

Questions we get asked

Can I build the crossover myself?

Most Melbourne councils require a contractor with public liability insurance and some require a council-registered contractor. Check your council's rules; it is rarely worth the saving.

How long does approval take?

One to four weeks is typical. Allow longer if a tree or service is involved, or if the council wants a site meeting.

Do I need a permit to replace an existing crossover like for like?

Yes, in almost every Melbourne council. The permit is about protecting council assets during the work, not just about new crossovers.